Most people think of GPS as satellites. The constellation is only half of it, though. The other half is a network of control and monitoring stations on the ground that tracks the spacecraft, uploads navigation data, and catches problems before receivers on the ground or in the air notice anything. Space Systems Command (SSC) has now started planning who will run that ground network for the next decade.
On Nov. 20, SSC posted a request for information and sources-sought notice on SAM.gov, the federal contracting portal, for a program called SPIDER. The name stands for "Sustaining PNT & Integrating with Development to Enhance Readiness," and PNT means position, navigation and timing. The notice (solicitation FA8823A071993) calls SPIDER the anticipated long-term successor to GCS II, the current GPS Control Segment Sustainment II contract. Responses are due Jan. 4, 2027.
What SPIDER is supposed to be
The notice says SPIDER is more than a contract renewal. SSC describes it as a "paradigm shift from pure hardware and software sustainment to a unified sustainment and continuous development integration model." In practice, the contractor must sustain the legacy ground systems and, under the same contract, continuously integrate developmental modifications from ongoing modernization efforts to support next-generation spacecraft.
That combination is the core of the plan. A sustainment contract has traditionally meant patching software, replacing hardware as it ages, and keeping operators supplied. Development work, the new capabilities that new satellites need, often ran on a separate track. SPIDER would put both under one contract.
The notice also states plainly where things are headed. According to SSC, the Space Force "has committed to sustaining and modernizing the existing, proven Global Positioning System (GPS) ground segment for the foreseeable future."
Timeline and contract structure
DefenseScoop reported on Nov. 24 that the Space Force has marked mid-2028 as the planned award window. The planned vehicle is a five-year indefinite-delivery/indefinite-quantity (IDIQ) contract plus another five-year optional ordering period, with work issued through multiple task orders. If both periods are used, SPIDER could run about ten years from award.
According to DefenseScoop, the notice asks for industry replies on any of six task areas at control stations and monitoring stations. They include systems engineering support, hardware and software upgrade integration, maintenance at control stations, monitoring of cyber threats, integrated logistics support, and management of government-furnished property. Most of the work would take place at Schriever Space Force Base in Colorado and Vandenberg Space Force Base in California.
The contract SPIDER would replace, GCS II, was first handed to Lockheed Martin in 2019. A follow-on to that award was slated to wrap in 2025, but the Space Force added three option years that extend performance through 2028. Lockheed told DefenseScoop it plans to respond to the sources-sought notice.
The GPS IIIF problem
The main technical driver is GPS IIIF, the next block of satellites, which Lockheed Martin builds. DefenseScoop reports that the sustainment system should pair with GPS IIIF, which, according to a Lockheed announcement, brings triple the accuracy and eight times the anti-jamming strength. Under the notice, the contractor must also oversee civil navigation signals and maintain resilience to electronic warfare and cyberattacks through consistent software upgrades.
The earlier generation is now fully in orbit. The Space Force and Lockheed launched the 10th and last GPS III satellite in April, according to DefenseScoop. The ground segment therefore has to support the GPS III satellites already flying while it prepares for the IIIF satellites that come next.
Some of that preparation is already paid for. Breaking Defense reported on Apr. 17, 2026, that Lockheed Martin's contract, awarded Apr. 8, is worth up to $105 million. It covers the satellites in orbit today as well as launch, early-orbit, and disposal operations for GPS IIIF. According to Lockheed's announcement, the contract expands on a decade of work under the Space Force's Architecture Evolution Plan (AEP), the ground system that Breaking Defense says commands and controls all GPS satellites, including the GPS IIIs.
The OCX backdrop
All of this follows years of trouble with OCX, the Next-Generation Operational Control System built by RTX. Breaking Defense recounted that OCX was originally supposed to be completed in 2016, and that its projected price tag has risen from $3.7 billion to almost $8 billion. An Air Force official told a House subcommittee in March that testing found "extensive system issues across all sub-systems, many of which have not been resolved." As of April, Breaking Defense reported, the Department of the Air Force was weighing whether to cancel OCX in favor of continuing to modernize AEP.
That history gives context to the wording of the SPIDER notice. A program office expecting a new ground system to take over soon would be unlikely to call the existing one "proven" and commit to it "for the foreseeable future." The notice itself does not mention OCX, so this is an inference, but it fits a Space Force that plans to keep upgrading the current ground segment under a contract designed for that, rather than wait for a full replacement.
Why It Matters
GPS underpins military navigation and precision weapons, and its civil signals serve a vast range of users worldwide. The satellites get most of the attention, but the ground segment decides whether the system works day to day and whether new satellite capabilities actually become usable. Chief of Space Operations Gen. Chance Saltzman said in April that as GPS IIIF and beyond go into orbit, "we're going to require new ground system upgrades," and that the Space Force wants them to be cyber secure.
SPIDER appears to be the Space Force's vehicle for that need. Combining sustainment and development under one contract is meant to keep upgrades flowing into a ground system that will stay in service longer than once planned. The approach carries its own risks. Running an operational system while continuously changing it is hard engineering, and the electronic-warfare and cyber requirements make the margin for error smaller.
The schedule matters too. Responses are due in early January, and the award is targeted for mid-2028. Until then, Lockheed's GCS II contract, extended by its added option years through 2028, remains in place. Lockheed has said it will respond to the notice. The responses SSC receives will show whether it gets a real competition for one of the most important contracts in space infrastructure.
Sources
- SAM.gov: Sustaining PNT & Integrating with Development to Enhance Readiness (SPIDER) RFI/Sources Sought, Space Systems Command
- DefenseScoop: Space Systems Command eyes mid-2028 for GPS sustainment upgrade contract
- Breaking Defense: Lockheed Martin nabs $105M ground system contract to support next-gen GPS